Monday, July 7, 2014

Well It's Monday the 7th of July. Concrete was supposed to come this morning but too much water from last nights rain remaining in trenches. Postponed to tomorrow afternoon. In the mean time we will contintue pumping out water and cleaning the forms. These pics are of the completed form work.


First layer of rebar 8 bars with 8" on center
Northeast wall completed


North wall

Foreman Nuts